A revised Legacy Pointe plan cuts the 300-room hotel and adds 330 apartments and a car dealership use. Spring Hill planners discuss it at 5:30 p.m. Monday.
The 300-room hotel planned for Legacy Pointe would be dropped under a revised plan for the 213-acre development at Saturn Parkway and Kedron Road. The plan would add 330 apartments and allow a car dealership with outdoor display.
Spring Hill’s Municipal Planning Commission discusses the request, PDA 2225-2026, at its work session at 5:30 p.m. Monday at City Hall, 199 Town Center Parkway. A work session is for discussion. The commission does not vote on the plan Monday.
City planning staff questioned several of the changes. The staff report in the Nov. 23 agenda packet (PDF) says the proposed design standards are “significantly different than what was previously approved.”
Overview
- What: a planned development amendment for Legacy Pointe, submitted by the engineering firm Kimley-Horn
- Where: east of The Crossings shopping center, west of Kedron Road and north of Saturn Parkway
- Main changes: no hotel, no pickleball courts, 330 more apartments, a smaller wholesale club and a car dealership use
- When: Planning Commission work session, 5:30 p.m. Monday, Nov. 23; no vote
- Next: the applicant must answer the commission’s comments by a Nov. 30 revision deadline
What would change
Legacy Pointe was earlier called Spring Hill Crossings and Project Smash. The Board of Mayor and Aldermen approved its preliminary plan on Dec. 19, 2022, with Ordinance 22-24. It has had four revisions since, the latest approved June 16, 2025. The site has been graded and several internal roads are open, staff wrote. Many commercial pads are ready but have no buildings yet.
The staff report compares the current phasing plan with the proposed one:
| Current plan | Proposed plan | |
|---|---|---|
| Homes | 1,514 | 1,589 |
| Commercial space | 589,285 square feet | 568,985 square feet |
| Hotel rooms | 300 | 0 |
| Pickleball courts | 12 | none listed |
| Wholesale club | 246,000 square feet with retail and restaurants | 166,000 square feet |
The first phases stay the same: 549 duplexes, townhomes and single-family homes, 64,000 square feet of self-storage, then 350 and 360 apartments. The new plan adds a phase of 330 apartments. The 205 active adult homes and 50 townhomes in the current plan do not appear in the proposed phasing table.
The applicant also wants to:
- add “Vehicle Dealership-With Outdoor Storage/Display” as an allowed use
- remove standalone parking lots and parking garages as a principal use
- revise the order in which the phases are built
Staff asked for the parking lot change. Staff said they do not oppose parking garages. On the dealership, the report says the use “is not ideal for the planned development.” Staff asked commissioners for their view.
Lower design standards
The applicant proposes looser rules for how commercial buildings look. The staff report lists the main changes:
| Standard | Current | Proposed |
|---|---|---|
| Longest blank wall | 15 feet | 25 feet, or 40 feet on buildings over 50,000 square feet |
| Ground-floor windows | at least 50% of the wall | at least 5% |
| Roofline variation | every 75 feet | every 150 feet along the main entrance |
| Parking in front of buildings | not allowed | allowed |
Materials such as corrugated metal, rough concrete panels and vinyl are limited on a building’s main surfaces. That limit started at 20%, rose to 30% and would now rise to 50%. Staff wrote that there “could be an opportunity to compromise in a manner that does not lower the design standards.”
Traffic and sewer
The applicant’s trip comparison puts the new plan at 31,540 vehicle trips a day. The 2023 plan was estimated at 38,996.
Estimated sewer use would fall from 418,582 gallons a day to 376,532. Staff want Spring Hill Water to check those figures. Sewer capacity is tight in the city, which is working on a wastewater deal with Columbia. The aldermen have called a special meeting on sewer for 6 p.m. Monday, Nov. 30, according to the city calendar.
Staff also warned about phasing. Many road and utility improvements at Legacy Pointe are tied to specific phases, the report said, and “completely changing the phasing could result in a delay or missed benchmark.”
Also on Monday’s agenda
The commission will consider PC Resolution 26-102. It would reclassify Crossings Boulevard and Crossings Circle, the two main roads through Legacy Pointe, from arterials to collectors in the city’s Major Thoroughfare Plan. Staff wrote that both were built to collector standards. The consultant that prepared the plan told staff it believes one of its maps colored the roads as arterials in error. The Transportation Advisory Committee recommended the change Nov. 16.
What it means for you
- Want a say? Speak after the staff report at Monday’s meeting, with five minutes per speaker, or email PCPublicComment@springhilltn.org.
- No decision yet. The plan comes back for a vote after the Nov. 30 revision deadline.
- If you shop at The Crossings or drive Kedron Road, the new plan would mean fewer daily trips than the approved one, by the applicant’s estimate.
The full packet is on the city’s Agenda Center. For work on the roads nearby, see road construction and closures.